Cost Keeping and Management Engineering: A Treatise for Engineers, Contractors and Superintendents Engaged in the Management of Engineering Construction |
Other editions - View all
Common terms and phrases
Aberthaw accounts actual cost amount bills Blacksmith Blacksmith Record blank blasting bookkeeping Brick cars cash cement cents charge chart column complete concrete Construction Service contract contractor copy cost keeping system cost records cubic yard Daily Report Date depreciation derrick distribution Dredge duplicate engineer Engineering-Contracting estimated excavation expense falsework feet foreman gang gives handling Helpers home office keeper key letter kind labor ledger machine material measured methods month number of units operation output pay roll payroll performance piece rate pipe plant Punch Card Purchase quarry received report card rock rule Sand scow sewer sheet shifting shovel shown in Fig steam steam shovel stone STONE SHIPPED superintendent supplies Teams timekeeper tion total cost unit cost unloading usually wages wagon Watchmen Water Boy Weather week weekly workmen York City
Popular passages
Page 42 - ... paid for the work. After analyzing the job, and determining the shortest time required to do each of the elementary operations of which it was composed, and then summing up the total, the writer became convinced that it was possible to turn ten pieces a day. To finish the forgings at this rate, however, the machinists were obliged to work at their maximum pace from morning to night, and the lathes were run as fast as the tools would allow, and under a heavy feed.
Page 198 - ... if the same efficiency is obtained from the men it is very easy to make a correction, or if the efficiency varies, judgment must be applied to determine the correct rate to use. It has been the writer's experience that although the rate of wages and cost of materials vary somewhat in different parts of the country, the variations frequently offset one another so nearly that the sum total of the unit cost obtained in one place may be used in another, very seldom needing correction. For Instance,...
Page 43 - But from the day they first turned ten pieces to the present time, a period of more than ten years, the men who understood their work have scarcely failed a single day to turn at this rate. Throughout that time until the beginning of the recent fall in the scale of wages throughout the country, the rate was not cut. " During this whole period, the competitors of the company never succeeded in averaging over half of this production per lathe, although they knew and even saw what was being done at...
Page 196 - The bookkeeper works these reports up into units of measurement, as cost of labor per cubic foot of concrete and number of cubic feet of concrete per barrel of cement, number of square feet of form work erected, etc., and from this it is easy to obtain the unit costs hereinafter given. The bookkeeper can take the reports of four or five jobs, employing in the aggregate 500 or...
Page 44 - Throughout the works, however, the principle of the differential rate was maintained, and was, and still is, fully appreciated by both the management and men. Through some error at the time of the general reduction of wages in 1893, the differential rate on the particular job above referred to was removed, and a straight piecework rate of 25 cts.
