Specifically , determine the approach to be adopted for involving the private
sector , the range of PSP activities , and the time frame ; ( viii ) Draw up a list of
pre - qualified private sector contractors ; ( ix ) Prepare Scope of Work and
bidding ...
Specifically , determine the approach to be adopted for involving the private
sector , the range of PSP activities , and the time frame ; ( viii ) Draw up a list of
pre - qualified private sector contractors ; ( ix ) Prepare Scope of Work and
bidding ...
Page 33
2.0 Scope of Work Basically , therefore , the scope is limited to making
improvement to the existing system of water cess administration , within the
existing rules and regulations . . The scope of Work will include : Working with the
DPCC to ...
2.0 Scope of Work Basically , therefore , the scope is limited to making
improvement to the existing system of water cess administration , within the
existing rules and regulations . . The scope of Work will include : Working with the
DPCC to ...
Page 40
3.0 Scope of Work The scope of work to be undertaken to meet the above
objectives , would be : ( i ) prepare a broad - brush assessment of Delhi's general
features , assessed risk factors and degree / level of exposure to those risk
factors ...
3.0 Scope of Work The scope of work to be undertaken to meet the above
objectives , would be : ( i ) prepare a broad - brush assessment of Delhi's general
features , assessed risk factors and degree / level of exposure to those risk
factors ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Other editions - View all
Common terms and phrases
action activities administration agencies Annex approach appropriate areas assessment authorities bidding documents Capacity Building carried Charter collection components concerned consultants coordination cost Delhi 21 departments detailed DPCC effective Environment environmental Environmental Health existing functions future GNCTD hazardous identified implementation Improvement industrial Information System infrastructure Initiating institutional Integrated involved issues laboratory land records maps monitoring months municipal municipal bodies objectives operation Outline Technical Assistance participation phase planning planning and management PMCU pollution possible prepare present priority private sector problems procedures programmes projects proposed recommended regulatory relevant Report resource responsibilities risks role Scope setting skills Slum staff Strategic strengthen surveys tasks Technical Assistance Annex term traffic transport units Upgrading urban various waste management water cess