Delhi Urban Environment and Infrastructure Improvement Project (DUEIIP).Government of India, Ministry of Environment and Forests and Government of National Capital Territory of Delhi, Planning Department, 2001 - City planning |
From inside the book
Results 1-3 of 5
Page 2
Part II - Scientific Development of a Landfill Site at Bhati Mines Therefore , there
is an urgent need to find other suitable sites for the disposal of city wastes
through the properly engineered and operated sanitary land fill method . 1.3
Alternative ...
Part II - Scientific Development of a Landfill Site at Bhati Mines Therefore , there
is an urgent need to find other suitable sites for the disposal of city wastes
through the properly engineered and operated sanitary land fill method . 1.3
Alternative ...
Page 12
Methane at a concentration of 5-15 % by volume of air forms an inflammable
mixture at normal atmospheric temperature and pressure . The gas tends to
escape through cracks and crevices in the surrounding area unless suitable
controlled ...
Methane at a concentration of 5-15 % by volume of air forms an inflammable
mixture at normal atmospheric temperature and pressure . The gas tends to
escape through cracks and crevices in the surrounding area unless suitable
controlled ...
Page
1 2 3 4 5 Name of Site Area , Depth and Life of Site Remarks Capacity Puthkhurd
54.6 Hectare 17 Months Soil is suitable for use as cover material . This site in 14
km by road from Bhalswa . It is a private agricultural land and hence the ...
1 2 3 4 5 Name of Site Area , Depth and Life of Site Remarks Capacity Puthkhurd
54.6 Hectare 17 Months Soil is suitable for use as cover material . This site in 14
km by road from Bhalswa . It is a private agricultural land and hence the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Other editions - View all
Common terms and phrases
additional airport alternative approach base Benefits Bhati Mines body bottom capacity carried cell Central Chattarpur Compost Plant construction continuous cost cover material Deep Delhi DELHI URBAN ENVIRONMENT Design drain Electricity environmental excavated existing Figure further Government ground water growth habitats Hectare Hence human identified impact Improvement included increase indicated Infrastructure investment land fill Landfill Site landfill sites Layer leachate limits located material Million Tonnes Mitigation Measures monitoring Months municipal waste NEERI noise operation option organic period PHASE pollution Preparation present Production Project proposed reclamation recovery reduce Report result road sand sanitary landfill Scientific Development Screening serve side Site at Bhati soil solid waste Source Stores Study suitable surface surrounding Table transportation treatment trees vehicle vicinity village volume waste disposal weigh bridge wide windrow workers Zone