Secondly , for the daily covering of deposited waste material can be made
available locally by excavating loose material from the second half of the pit .
Preparation to start the landfilling will need the following operations . 4.3.2
Construction of ...
Secondly , for the daily covering of deposited waste material can be made
available locally by excavating loose material from the second half of the pit .
Preparation to start the landfilling will need the following operations . 4.3.2
Construction of ...
Page 18
Daily covering material would not have to be brought to the site due to the
existence of loose material already in the pits . Material for cover and cell
construction can often amount to over 30 % of the SLF operational cost . 6.1.2
Operation ...
Daily covering material would not have to be brought to the site due to the
existence of loose material already in the pits . Material for cover and cell
construction can often amount to over 30 % of the SLF operational cost . 6.1.2
Operation ...
Page
1 2 3 4 5 Name of Site Area , Depth and Life of Site Remarks Capacity Puthkhurd
54.6 Hectare 17 Months Soil is suitable for use as cover material . This site in 14
km by road from Bhalswa . It is a private agricultural land and hence the ...
1 2 3 4 5 Name of Site Area , Depth and Life of Site Remarks Capacity Puthkhurd
54.6 Hectare 17 Months Soil is suitable for use as cover material . This site in 14
km by road from Bhalswa . It is a private agricultural land and hence the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Other editions - View all
Common terms and phrases
additional airport alternative approach base Benefits Bhati Mines body bottom capacity carried cell Central Chattarpur Compost Plant construction continuous cost cover material Deep Delhi DELHI URBAN ENVIRONMENT Design drain Electricity environmental excavated existing Figure further Government ground water growth habitats Hectare Hence human identified impact Improvement included increase indicated Infrastructure investment land fill Landfill Site landfill sites Layer leachate limits located material Million Tonnes Mitigation Measures monitoring Months municipal waste NEERI noise operation option organic period PHASE pollution Preparation present Production Project proposed reclamation recovery reduce Report result road sand sanitary landfill Scientific Development Screening serve side Site at Bhati soil solid waste Source Stores Study suitable surface surrounding Table transportation treatment trees vehicle vicinity village volume waste disposal weigh bridge wide windrow workers Zone