Delhi Urban Environment and Infrastructure Improvement Project (DUEIIP).Government of India, Ministry of Environment and Forests and Government of National Capital Territory of Delhi, Planning Department, 2001 - City planning |
From inside the book
Results 1-3 of 4
Page 15
It is proposed to provide a 40 tonnes weigh bridge with a facility to provide an
automatic printout indicating the weight of ... sanitary facilities , vehicle repair
workshop and stores and to provide first aid and recreational facilities for the
workers .
It is proposed to provide a 40 tonnes weigh bridge with a facility to provide an
automatic printout indicating the weight of ... sanitary facilities , vehicle repair
workshop and stores and to provide first aid and recreational facilities for the
workers .
Page
Construction workers should be provided sanitation facilities . . 0 o Aquatic
Ecology Soil -3 +1 No impact envisaged . No mitigation measures required .
There should be proper sanitation with collection and disposal of waste from the
...
Construction workers should be provided sanitation facilities . . 0 o Aquatic
Ecology Soil -3 +1 No impact envisaged . No mitigation measures required .
There should be proper sanitation with collection and disposal of waste from the
...
Page
Proper sanitation facilities should be provided at construction camp . . . Notes :
Const - Construction Phase Long - Long Term Severity of negative impacts
increasing from - 1 to -5 . Benefits increasing from 1 to 5 February 2001 page 24
Delhi ...
Proper sanitation facilities should be provided at construction camp . . . Notes :
Const - Construction Phase Long - Long Term Severity of negative impacts
increasing from - 1 to -5 . Benefits increasing from 1 to 5 February 2001 page 24
Delhi ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Other editions - View all
Common terms and phrases
additional airport alternative approach base Benefits Bhati Mines body bottom capacity carried cell Central Chattarpur Compost Plant construction continuous cost cover material Deep Delhi DELHI URBAN ENVIRONMENT Design drain Electricity environmental excavated existing Figure further Government ground water growth habitats Hectare Hence human identified impact Improvement included increase indicated Infrastructure investment land fill Landfill Site landfill sites Layer leachate limits located material Million Tonnes Mitigation Measures monitoring Months municipal waste NEERI noise operation option organic period PHASE pollution Preparation present Production Project proposed reclamation recovery reduce Report result road sand sanitary landfill Scientific Development Screening serve side Site at Bhati soil solid waste Source Stores Study suitable surface surrounding Table transportation treatment trees vehicle vicinity village volume waste disposal weigh bridge wide windrow workers Zone